The time has finally come. The construction thriller is entering its final phase.
You are among the very first friends of the Schlossanger to find out the opening date of the ALP SPA.

The schedule for the next 6 weeks is set and the ALP SPA starts on Friday 17.4.2025.

We are still super sporty on the road. But we know that we can rely on our craftsmen. So if you want, you can book now and experience the start soon.

In the meantime, some progress has been made on the construction site. In contrast to other crime thrillers, however, the outcome, the victims and the perpetrators are obvious and known in advance.

The sun has been shining since today and the temperatures are clearly rising. For this reason, there are now 6 excavators on the Schlossanger Grund again. Details of the outdoor area will be discussed this week and work will begin immediately.

As you can see, the stone wall between the sauna house and the earth sauna has grown and the waterfall is already visible.
The area around the earth sauna is being filled in this week, but you can also follow that via the webcam.
Speaking of excavating: At the base plate of the suite house, which we are planning for 2026, you now have a view of the great Tyrolean mountains. It's still a while away, but the anticipation is growing here too.

This morning I was already in the future new Sterntaler to enjoy the view of the sunrise. The suite will be a little smaller, but at least just as exciting as before.
Let me tell you this much: sleeping under the stars will remain the same, but a little higher and different.

The HOFER DACH waterproofers are working at full throttle on the entire roof area. Waterproofing and insulating is a huge amount of work, but the aim is to create the perfect substrate for future greenery.

The earth sauna is currently being tiled in preparation for the installation of the furnishings. The first production images of the round inner dome are already very impressive. As soon as it is installed, you will of course get to see them.

The electrician's cables are piled up in the sauna house and the ceilings are being prepared for closing, as you can see in the pictures. It's a complete mystery to me who can still see through the technology here, but as we all know, it's the result that counts.

The pool builders have now finished foiling the very elaborate gutter and are now working on the surfaces. We will probably see a lot more next week, especially as part of the temporary roof will then be removed.

There are now holes in the access via the stairs and the elevator builder is in full swing.
It's unbelievable how one man can install the entire elevator over 4 floors and 6 exit points. We'll see if it's up and running in 2 weeks' time.

So much for today. The continuation will follow and will now have a higher frequency depending on the construction phase.

With sunny greetings from the Schlossanger
Your Bernd